September 2012 - Contract from Samsung C&T Corporation Saudi Arabia

EGYPTROL was awarded a contract from "Samsung C&T Corporation Saudi Arabia" for providing commissioning & operation services for "Qurayyah combined cycle gas-fired power plant 4500 MW".

ProjectQurayyah Independent Power Project
LocationQurayyah, East Coast Kingdom of Saudi Arabia
Project OwnerHAJR Electricity Production Company
Project PeriodOctober 2011 – June 2014
Planned Commissioning PeriodMay 2013 – July 2014
EPC ContractorSamsung C&T
Project Facilities12 nos. SGT6 5000F GTs
12 HRSGs of double pressure design
6 nos. SST6 4000 STs
Balance of Plant


January 2012 - Available Online CVs count exceeded 1,000

Our online available CV's of technical professionals (mostly power plants experience) exceeded 1000 CVs. They are all available to support our customers’ construction, commissioning, operation and annual inspections activities.


December 2011 - Multipharma new Warehouse Building

EGYPTROL was awarded the design of electromechanical system for Multipharma new Warehouse Building, the scope is to prepare technical RFP documents for HVAC, Fire Fighting, Plumbing, Electrical, and Low Current systems.


December 2011 - King Abdu Al-Aziz University (KAU)

December 2011 - King Abdu Al-Aziz University (KAU) EGYPTROL was awarded a contract from WESSAM Consulting for the Aquarium Building of King Abdu Al-Aziz University (KAU), College of Marine Science. The scope is to prepare technical RFP documents for HVAC, Fire Fighting, Plumbing, Electrical, and Low Current systems.


December 2011 - Ansaldo Energia S.p.A. Italy

EGYPTROL was awarded a contract from “ Ansaldo Energia S.p.A. Italy” for providing commissioning and operation staff for “6th of October Simple Cycle Power Plant 4x150MW” Gas turbines and auxiliary systems including the water treatment.


October 2011 - TAM Environmental

EGYPTROL was awarded a contract from TAM Environmental for Matrouh 24000m3 Desalination Plant. The scope is to support TAM in detailed Engineering for electrical, mechanical equipment, piping and Instrumentation.


October 2011 - PESCO

EGYPTROL was awarded a contract from PESCO for Juba Power Plant 4x8MW Diesel Generator (Heavy Oil), the scope is to participate in preparation of power plant PDR (preliminary Design Report) Electrical, Mechanical, Control and Civil.


October 2011 - HALLA MALL

EGYPTROL was awarded a contract for Halla mall (5th settlement), the scope is to prepare technical RFP documents for HVAC, Fire Fighting, Plumbing, Electrical, and Low Current systems.


October 2011 - Ansaldo Caldaie S.P.A. Italy/AC Boilers Egypt S.A.E.

EGYPTROL was awarded a contract from CP-105 “Ansaldo Caldaie S.p.A. Italy /AC Boilers Egypt S.A.E.” for Mechanical commissioning and operation of two boilers each of 2067t/hr at Abu Qir units 6&7 (2 x 650MW Thermal Power Plant).


September 2011 - ISO Certified

EGYPTROL is Certified for ISO 9001:2008 by Germanischer Lioyd SE, On Sept. 13, 2011


September 2011 - Move to new building

Egyptrol recently moved to its new Building in Nasr City. The modern and spacious new office building, designed to make our employees more comfortable to accomplish the best work for our clients.


August 2011 - Tharwa Breda Factory

Thrwa Breda Company Awarded a contract to EGYPTROL to revise electrical system for its steel fabrication workshop at Badr city and issue revised BOQ for contractors pricing.


June 2011 - Engineering Solution ES

EGYPTROL was awarded a contract from ES for Al-Nafle Building Complex to prepare technical RFP documents for Fire Fighting, Plumbing, Electrical, and Low Current systems.


June 2011 - KN (Kharafi National)

EGYPTROL was awarded a contract from Kharafi National for West Damietta Power Plants to prepare hydraulic calculations for the following systems:
1. Service water hydraulic calculations.
2. Demin water hydraulic calculations.
3. Fuel oil hydraulic calculations.
4. Deep Well Calculations.


May 2011 - AUG (Allied United Group) Pharmaceutical Group 6th of October Facility Project

AUG awarded a contract to EGYPTROL for consultancy services for project site activities supervision for Electrical, Fire Fighting and Plumbing services.


February 2011 - Arabian Construction Company ACC

ACC intending to participate in Benha Power Plant CP-102 bid they Awarded EGYPTROL a contract to prepare detailed BOQ for HVAC, electrical and plumbing works related to contract package (CP102).


January 2011 - Engineering Consultant Group and Value Engineering (VECG)

EGYPTROL was awarded a contract from VECG for Al-Haram (MECCA) Diesel Generators Plant to prepare Piping workshop drawings for the following systems:
1. Fuel oil system.
2. Lubricating oil system.
3. Breathing and exhaust system.
4. Cooling water system.
5. Compressed air system.


January 2011 - Kharafi National

EGYPTROL was awarded a contract from Kharafi National for West Damietta Power Plants to prepare hydraulic calculations for the following systems:
Shabab PP:
1. Service water hydraulic calculations.
2. Demin water hydraulic calculations.
3. Fuel oil hydraulic calculations.
4. Fire Fighting hydraulic calculations.
5. Sump pumps hydraulic calculations.
6. Pressure drop on washing skid calculations.

Damietta PP:
1. Service water hydraulic calculations.
2. Demin water hydraulic calculations.
3. Fuel oil hydraulic calculations.